Breakup

16.9.1 Standard French polishing to Wooden board surface by three coats over a coat of priming including putty, cleaning, finishing and polishing with sand paper etc. all complete in all floors and accepted by the Engineer-in-charge.

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 French powder French powder 0.25 kg 30 per kg 30 7.5
2 Spirit Spirit 4 lbs 150 per Ib 150 600
3 Gala Gala 0.15 kg 900 per kg 900 135
4 Karpa Karpa 0.05 kg 550 per kg 550 27.5
5 Sand paper Sand paper 4 nos 16 each 16 64
6 Putty Putty 0.5 kg 107 per kg 107 53.5
7 Markin cloth Markin cloth 0.5 yard 12 per yard 12 6
8 Cotton Cotton 0.03 lbs 105 per lbs 105 3.15
9 Painter Painter 2 nos 700 per day 700 1400
10 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper 1.75 nos 550 per day 550 962.5
11 Ordinary labour Scaffolding, sundries etc. 1 LS 550 per day 165 165
Sub-Total 3424.15
Contractor's Profit 10% 0.1 342.42
Contractor's Overhead Expenses 3.5% 0.035 119.85
Total 3886.42
Add VAT with adjustment factor. 1.08108 7.5% 0.075 315.11
Grand Total 4201.53
Rate per sft 42.02
Rate per sqm 452.3