Considering 100 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | French powder French powder | 0.25 | kg | 30 | per kg | 30 | 7.5 | |
| 2 | Spirit Spirit | 4 | lbs | 150 | per Ib | 150 | 600 | |
| 3 | Gala Gala | 0.15 | kg | 900 | per kg | 900 | 135 | |
| 4 | Karpa Karpa | 0.05 | kg | 550 | per kg | 550 | 27.5 | |
| 5 | Sand paper Sand paper | 4 | nos | 16 | each | 16 | 64 | |
| 6 | Putty Putty | 0.5 | kg | 107 | per kg | 107 | 53.5 | |
| 7 | Markin cloth Markin cloth | 0.5 | yard | 12 | per yard | 12 | 6 | |
| 8 | Cotton Cotton | 0.03 | lbs | 105 | per lbs | 105 | 3.15 | |
| 9 | Painter Painter | 2 | nos | 700 | per day | 700 | 1400 | |
| 10 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper | 1.75 | nos | 550 | per day | 550 | 962.5 | |
| 11 | Ordinary labour Scaffolding, sundries etc. | 1 | LS | 550 | per day | 165 | 165 | |
| Sub-Total | 3424.15 | |||||||
| Contractor's Profit | 10% | 0.1 | 342.42 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 119.85 | |||||
| Total | 3886.42 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 315.11 | ||||
| Grand Total | 4201.53 | |||||||
| Rate per sft | 42.02 | |||||||
| Rate per sqm | 452.3 | |||||||