16.9.2 Premium French polishing to door and window frames, shutter and any other wooden surface by three coats over a coat of priming including putty, cleaning, finishing and polishing with sand paper etc. all complete in all floors and accepted by the Engineer-in-charge.

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 French powder French powder 0.25 kg 30 per kg 30 7.5
2 Spirit Spirit 4 lbs 150 per Ib 150 600
3 Gala Gala 0.25 kg 900 per kg 900 225
4 Karpa Karpa 0.05 kg 550 per kg 550 27.5
5 Sand paper Sand paper 4 no 16 each 16 64
6 Putty Putty 0.5 kg 107 per kg 107 53.5
7 Markin cloth Markin cloth 0.5 yard 12 per yard 12 6
8 Cotton Cotton 0.03 lbs 105 per lbs 105 3.15
9 Painter Painter 2 nos 700 per day 700 1400
10 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper 2.5 nos 550 per day 550 1375
11 Ordinary labour Scaffolding, sundries etc. 1 LS 550 per day 165 165
Sub-Total 3926.65
Contractor's Profit 10% 0.1 392.67
Contractor's Overhead Expenses 3.5% 0.035 137.43
Total 4456.75
Add VAT with adjustment factor. 1.08108 7.5% 0.075 361.36
Grand Total 4818.11
Rate per sft 48.18
Rate per sqm 518.61