Breakup

16.10.3 Matt

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Sand paper Sand paper 4 nos 16 each 16 64
2 Markin cloth Markin cloth 0.5 yard 12 per yard 12 6
3 Painter Painter 1 no 700 per day 700 700
4 Ordinary labour Ordinary labour 0.75 no 550 per day 550 412.5
5 Ordinary labour Scaffolding, sundries, T & P etc. 1 LS 550 per day 165 165
6 Wood varnishing: Matt ( alkyd based) Cost of varnish: Matt 1.3 liter 290 per litre 290 377
7 Thinner for alkyd based wood varnishing Thinner 0.35 liter 131 per litre 131 45.85
Sub-Total 1770.35
Contractor's Profit 10% 0.1 177.03
Contractor's Overhead Expenses 3.5% 0.035 61.96
Total 2009.34
Add VAT with adjustment factor. 1.08108 7.5% 0.075 162.92
Grand Total 2172.26
Rate per sft 21.72
Rate per sqm 233.79
Help