02.19.2 Bailing out water by 1 cusec electricity operated pump including hire charge of pump, fuel, operator, spares and maintenance etc. all complete and accepted by the Engineer-in-charge.

Considering 1 day operation = 8 hrs.

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Hire charge of electricity operated 1 cusec capacity water pump Hire charge of pump including suction and delivery pipe, connection, switch 1 day 850 per day 850 850
3 Machine operator Pump operator 1 no 700 per day 700 700
4 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper 1 no 550 per day 550 550
5 Skilled labour Skilled labour for maintaining drainage 1 no 600 per day 600 600
6 Ordinary labour Provide drainage facilities and connection to discharge facilities 1 LS 550 per day 429.69 429.69
7 Ordinary labour Tools and plant, sundries etc. 1 LS 550 per day 257.81 257.81
2 Electricity, lubricant, spares, maintenance etc. LS 300
Sub-Total 3687.5
Contractor's Profit 10% 0.1 368.75
Contractor's Overhead Expenses 3.5% 0.035 129.06
Total 4185.31
Add VAT with adjustment factor. 1.08108 7.5% 0.075 339.35
Grand Total 4524.66
Rate per hour 565.63
Rate per hour 565.63