Considering 1 day operation = 8 hrs.
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Hire charge of electricity operated 1 cusec capacity water pump Hire charge of pump including suction and delivery pipe, connection, switch | 1 | day | 850 | per day | 850 | 850 | |
| 3 | Machine operator Pump operator | 1 | no | 700 | per day | 700 | 700 | |
| 4 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper | 1 | no | 550 | per day | 550 | 550 | |
| 5 | Skilled labour Skilled labour for maintaining drainage | 1 | no | 600 | per day | 600 | 600 | |
| 6 | Ordinary labour Provide drainage facilities and connection to discharge facilities | 1 | LS | 550 | per day | 429.69 | 429.69 | |
| 7 | Ordinary labour Tools and plant, sundries etc. | 1 | LS | 550 | per day | 257.81 | 257.81 | |
| 2 | Electricity, lubricant, spares, maintenance etc. | LS | 300 | |||||
| Sub-Total | 3687.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 368.75 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 129.06 | |||||
| Total | 4185.31 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 339.35 | ||||
| Grand Total | 4524.66 | |||||||
| Rate per hour | 565.63 | |||||||
| Rate per hour | 565.63 | |||||||