Breakup

16.12 White washing by three coats, lime mixture prepared at least 12 hours before use, slacking stone lime, supplying of gums, blue, stirring thoroughly, removing the floating materials from the mixer, surface cleaning to free from all foreign materials before application of each coat, applying one vertical and one horizontal wash for each coat and successive coat is to be applied after drying up of previous coat including hair brass, providing necessary scaffolding and cleaning plinth, floors, doors, windows, portions and ventilators by washing, rubbing, oiling if necessary after white wash for all floors including cost of water, electricity and other charges etc. complete in all respect in all floors and accepted by the Engineer-in-charge.

Considering 1000 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Slaked lime Slaked lime 18.66 kg 25 per kg 25 466.5
2 Gum Gum 0.3 kg 200 per kg 200 60
3 Blue Blue 0.2 kg 200 per kg 200 40
4 Mason / Mosaic mistry Labour : Mason 1 no 700 per day 700 700
5 Ordinary labour Ordinary labour 1 no 550 per day 550 550
6 Ordinary labour Scaffolding, sundries, local carriage etc. 1 LS 550 per day 137.5 137.5
Sub-Total 1954
Contractor's Profit 10% 0.1 195.4
Contractor's Overhead Expenses 3.5% 0.035 68.39
Total 2217.79
Add VAT with adjustment factor. 1.08108 7.5% 0.075 179.82
Grand Total 2397.61
Rate per sft 2.4
Rate per sqm 25.83