Considering 100 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Painter Painter | 0.5 | no | 700 | per day | 700 | 350 | |
| 2 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Painter Helper | 0.5 | no | 550 | per day | 550 | 275 | |
| 3 | Ordinary labour Scaffolding, sundries etc | 1 | LS | 550 | per day | 859.38 | 859.38 | |
| 4 | Self leveling epoxy coating (3 mm thickness) Self Leveling Epoxy Coating (3mm thickness) | 100 | sft | 135 | per sft | 135 | 13500 | |
| Sub-Total | 14984.38 | |||||||
| Contractor's Profit | 10% | 0.1 | 1498.44 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 524.45 | |||||
| Total | 17007.27 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 1378.97 | ||||
| Grand Total | 18386.24 | |||||||
| Rate per sft | 183.86 | |||||||
| Rate per sqm | 1979.07 | |||||||