Considering 100 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Painter Painter | 0.75 | no | 700 | per day | 700 | 525 | |
| 2 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Painter Helper | 0.75 | no | 550 | per day | 550 | 412.5 | |
| 3 | Ordinary labour Scaffolding, sundries etc | 1 | LS | 550 | per day | 859.38 | 859.38 | |
| 4 | Self leveling epoxy coating (4 mm thickness) Self Leveling Epoxy Coating (4mm thickness) | 100 | sft | 161 | per sft | 161 | 16100 | |
| Sub-Total | 17896.88 | |||||||
| Contractor's Profit | 10% | 0.1 | 1789.69 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 626.39 | |||||
| Total | 20312.96 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 1647 | ||||
| Grand Total | 21959.96 | |||||||
| Rate per sft | 219.6 | |||||||
| Rate per sqm | 2363.77 | |||||||