Considering 100 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Painter Painter | 1 | no | 700 | per day | 700 | 700 | |
| 2 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Painter Helper | 1 | no | 550 | per day | 550 | 550 | |
| 3 | Ordinary labour Scaffolding, sundries etc | 1 | LS | 550 | per day | 859.38 | 859.38 | |
| 4 | Self leveling epoxy coating (5 mm thickness) Self Leveling Epoxy Coating (5mm thickness) | 100 | sft | 225 | per sft | 225 | 22500 | |
| Sub-Total | 24609.38 | |||||||
| Contractor's Profit | 10% | 0.1 | 2460.94 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 861.33 | |||||
| Total | 27931.65 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 2264.73 | ||||
| Grand Total | 30196.38 | |||||||
| Rate per sft | 301.96 | |||||||
| Rate per sqm | 3250.3 | |||||||