Break-up for 100 sft Area
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Painter Painter | 2 | no | 700 | per day | 700 | 1400 | |
| 2 | Ordinary labour Ordinary labour | 1 | no | 550 | per day | 550 | 550 | |
| 3 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper | 2 | no | 550 | per day | 550 | 1100 | |
| 4 | Fluoroscent paint Fluorocent paint | 2 | liter | 1375 | per litre | 1375 | 2750 | |
| 5 | Sealer for acrylic plastic emulsion paint Sealer | 0.82 | liter | 172 | per litre | 172 | 141.04 | |
| 6 | Thinner for oil-based paint (turpentine) for general purpose Thinner | 0.6 | liter | 131 | per litre | 131 | 78.6 | |
| 7 | Hire charge of paint spray machine Hire charge of paint spray Machine | 2 | days | 700 | per day | 700 | 1400 | |
| 8 | T & P local carriege Sundries | LS | 150 | |||||
| Sub-Total | 7569.64 | |||||||
| Contractor's Profit | 10% | 0.1 | 756.96 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 264.94 | |||||
| Total | 8591.54 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 696.61 | ||||
| Grand Total | 9288.15 | |||||||
| Rate per sft | 92.88 | |||||||
| Rate per sqm | 999.76 | |||||||