Considering 100 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | High performance elastomeric cementitious waterproof coating High performance elastomeric cementitious waterproof coating | 16.5 | kg | 225 | per kg | 225 | 3712.5 | |
| 2 | Skilled technician Labour : Skilled Technician | 0.5 | no | 1200 | per day | 1200 | 600 | |
| 3 | Skilled labour Skilled labour | 1 | no | 600 | per day | 600 | 600 | |
| 4 | Ordinary labour Local carriage, sundries, T&P etc. | 1 | LS | 550 | per day | 550 | 550 | |
| Sub-Total | 5462.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 546.25 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 191.19 | |||||
| Total | 6199.94 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 502.7 | ||||
| Grand Total | 6702.64 | |||||||
| Rate per sft | 67.03 | |||||||
| Rate per sqm | 721.51 | |||||||