Breakup

03.1.1 One layer brick flat soling in foundation or in floor with first class/picked jhama bricks (BDS 208) including preparation of bed and filling the interstices with local sand, leveling etc. complete and accepted by the Engineer-in-charge

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 1st class/Picked jhama standard bricks Bricks 300 nos 10000 per % 0 nos 10 3000
2 Sand (F.M. 0.8) Fine sand (FM 0.8) 5 cft 1670 per % cft 16.7 83.5
3 Mason / Mosaic mistry Mason 0.25 no 700 per day 700 175
4 Skilled labour Skilled labour 0.5 no 600 per day 600 300
5 Ordinary labour Local carriage, sundries, T & P etc. 1 LS 550 per day 60.5 60.5
Sub-Total 3619
Contractor's Profit 10% 0.1 361.9
Contractor's Overhead Expenses 3.5% 0.035 126.67
Total 4107.57
Add VAT with adjustment factor. 1.08108 7.5% 0.075 333.05
Grand Total 4440.62
Rate per sft 44.41
Rate per per sqm 478.03