Considering 100 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 1st class/Picked jhama standard bricks Bricks | 300 | nos | 10000 | per % 0 nos | 10 | 3000 | |
| 2 | Sand (F.M. 0.8) Fine sand (FM 0.8) | 5 | cft | 1670 | per % cft | 16.7 | 83.5 | |
| 3 | Mason / Mosaic mistry Mason | 0.25 | no | 700 | per day | 700 | 175 | |
| 4 | Skilled labour Skilled labour | 0.5 | no | 600 | per day | 600 | 300 | |
| 5 | Ordinary labour Local carriage, sundries, T & P etc. | 1 | LS | 550 | per day | 60.5 | 60.5 | |
| Sub-Total | 3619 | |||||||
| Contractor's Profit | 10% | 0.1 | 361.9 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 126.67 | |||||
| Total | 4107.57 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 333.05 | ||||
| Grand Total | 4440.62 | |||||||
| Rate per sft | 44.41 | |||||||
| Rate per per sqm | 478.03 | |||||||