17.2 Preparation and making gravel pack for roof top gardening with supply of 25 mm down graded pea gravels including sieving, washing, compacting etc. complete as per standard specification and accepted by the Engineer-in-charge. Ground floor

Considering 2.8 cum

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Pea-gravel Cost of pea-gravels including 10% for compaction 3.08 cum 9345 per % cft 3300.19 10164.59
2 Skilled labour Labour for packing of peagravels with care: Skilled labour 2 nos 600 per day 600 1200
3 Ordinary labour Local carriage, T & P 1 LS 550 per day 165 165
Sub-Total 11529.59
Contractor's Profit 10% 0.1 1152.96
Contractor's Overhead Expenses 3.5% 0.035 403.54
Total 13086.09
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1061.03
Grand Total 14147.12
Rate per cum 5052.5
Rate per cum 5052.5