Considering 2.8 cum
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Pea-gravel Cost of pea-gravels including 10% for compaction | 3.08 | cum | 9345 | per % cft | 3300.19 | 10164.59 | |
| 2 | Skilled labour Labour for packing of peagravels with care: Skilled labour | 2 | nos | 600 | per day | 600 | 1200 | |
| 3 | Ordinary labour Local carriage, T & P | 1 | LS | 550 | per day | 165 | 165 | |
| Sub-Total | 11529.59 | |||||||
| Contractor's Profit | 10% | 0.1 | 1152.96 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 403.54 | |||||
| Total | 13086.09 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 1061.03 | ||||
| Grand Total | 14147.12 | |||||||
| Rate per cum | 5052.5 | |||||||
| Rate per cum | 5052.5 | |||||||