Considering 2.8 cum
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Ordinary labour Add for each addl. floor above ground floor | 1 | per cum | 550 | per day | 59.58 | 59.58 | |
| Sub-Total | 59.58 | |||||||
| Contractor's Profit | 10% | 0.1 | 5.96 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 2.09 | |||||
| Total | 67.63 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 5.48 | ||||
| Grand Total | 73.11 | |||||||
| Rate per cum | 26.07 | |||||||
| Rate per cum | 26.07 | |||||||