Breakup

17.2.1.1 Add for each additional floor above ground floor

Considering 2.8 cum

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Ordinary labour Add for each addl. floor above ground floor 1 per cum 550 per day 59.58 59.58
Sub-Total 59.58
Contractor's Profit 10% 0.1 5.96
Contractor's Overhead Expenses 3.5% 0.035 2.09
Total 67.63
Add VAT with adjustment factor. 1.08108 7.5% 0.075 5.48
Grand Total 73.11
Rate per cum 26.07
Rate per cum 26.07