Breakup

17.4.1.1 Add for each additional floor above ground floor

Considering 100 cft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Ordinary labour Add for each addl. floor above ground floor 1 per cum 550 per day 119.16 119.16
Sub-Total 119.16
Contractor's Profit 10% 0.1 11.92
Contractor's Overhead Expenses 3.5% 0.035 4.17
Total 135.25
Add VAT with adjustment factor. 1.08108 7.5% 0.075 10.97
Grand Total 146.22
Rate per cft 1.46
Rate per cum 51.56