Breakup

03.1.2 One layer brick flat soling in foundation or in floor with sand cement solid block (SCSB) (250x115x115)mm including preparation of bed and filling the interstices with local sand, leveling etc. complete and accepted by the Engineer-in-charge

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Sand cement solid block (SCSB) (250x115x115)mm SCSB 290 nos 12000 per % 0 nos 12 3480
2 Sand (F.M. 0.8) Fine sand (FM 0.8) 4.9 cft 1670 per % cft 16.7 81.83
3 Mason / Mosaic mistry Mason 0.25 no 700 per day 700 175
4 Skilled labour Skilled labour 0.5 no 600 per day 600 300
5 Ordinary labour Local carriage, sundries, T & P etc. 1 LS 550 per day 60.5 60.5
Sub-Total 4097.33
Contractor's Profit 10% 0.1 409.73
Contractor's Overhead Expenses 3.5% 0.035 143.41
Total 4650.47
Add VAT with adjustment factor. 1.08108 7.5% 0.075 377.06
Grand Total 5027.53
Rate per sft 50.28
Rate per per sqm 541.21
Help