Breakup

18.1.2.1 12 mm thick melamine board ceiling

Consider 16'-0" x 10'-0"= 160 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Melamine board (12 mm thick): 8' -0" x 4'-0" size, 700kg/m3 Materials: Malamine board (12 mm thick): 8' -0" x 4'-0" size 5 pcs 2150 per pc 2150 10750
2 T-section (main T) for false ceiling(Anodized at any colour) Aluminium section & accessories : 1" main T-section (0.6 mm) 64 rft 28 per foot 28 1792
3 T-section (cross T) for false ceiling(Anodized at any colour) 1" cross T-section (0.6 mm) 30 rft 24 per foot 24 720
4 L-section for wall and ceiling(Anodized at any colour) 1" L-section (0.6 mm) 63 rft 23 per foot 23 1449
5 L-section for wall and ceiling(Anodized at any colour) Rivet 63 LS 23 per foot 3.19 200.97
6 G.I. wire G.I. wire 1.5 kg 120 per kg 120 180
7 Screws 1.5" screw 125 nos 1 each 1 125
8 Rowel plug Rowel plug 150 nos 1 each 1 150
9 Wall bit (9/64) Wall bit (6 mm) 2 nos 42 per pc 42 84
10 Skilled technician Skilled technician 2 nos 1200 per day 1200 2400
11 Carpenter Carpenter 6 nos 700 per day 700 4200
12 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to carpenter 18 nos 550 per day 550 9900
13 Scaffolding LS 400
14 Carrying to site in/c sundries LS 500
Sub-Total 32850.97
Contractor's Profit 10% 0.1 3285.1
Contractor's Overhead Expenses 3.5% 0.035 1149.78
Total 37285.85
Add VAT with adjustment factor. 1.08108 7.5% 0.075 3023.17
Grand Total 40309.02
Rate per sft 251.93
Rate per sqm 2711.77