Consider 10'-0" x 10'-0"= 100 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | T-section (main T) for false ceiling(Anodized at any colour) Main T-section: 4 x 10'- 0"= 40.00 rft | 40 | rft | 28 | per foot | 28 | 1120 | |
| 2 | T-section (cross T) for false ceiling(Anodized at any colour) Coss T-section 4 x 10' - 0"= 40.00 rft | 40 | rft | 24 | per foot | 24 | 960 | |
| 3 | L-section for wall and ceiling(Anodized at any colour) Angle or L-section: 4 x 10'- 0"= 40.00 rft | 40 | rft | 23 | per foot | 23 | 920 | |
| 4 | 9 mm thick gypsum board Gypsum board | 100 | sft | 36 | per sft | 36 | 3600 | |
| 5 | Skilled technician Skilled technician | 0.25 | nos | 1200 | per day | 1200 | 300 | |
| 6 | Carpenter Carpenter | 0.5 | nos | 700 | per day | 700 | 350 | |
| 7 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Carpenter helper | 1.5 | nos | 550 | per day | 550 | 825 | |
| 8 | Scaffolding | LS | 300 | |||||
| 9 | Carrying to site in/c sundries | LS | 500 | |||||
| Sub-Total | 8875 | |||||||
| Contractor's Profit | 10% | 0.1 | 887.5 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 310.63 | |||||
| Total | 10073.13 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 816.74 | ||||
| Grand Total | 10889.87 | |||||||
| Rate per sft | 108.9 | |||||||
| Rate per sqm | 1172.2 | |||||||