Breakup

18.1.2.3 9 mm thick plain gypsum board ceiling

Consider 10'-0" x 10'-0"= 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 T-section (main T) for false ceiling(Anodized at any colour) Main T-section: 4 x 10'- 0"= 40.00 rft 40 rft 28 per foot 28 1120
2 T-section (cross T) for false ceiling(Anodized at any colour) Coss T-section 4 x 10' - 0"= 40.00 rft 40 rft 24 per foot 24 960
3 L-section for wall and ceiling(Anodized at any colour) Angle or L-section: 4 x 10'- 0"= 40.00 rft 40 rft 23 per foot 23 920
4 9 mm thick gypsum board Gypsum board 100 sft 36 per sft 36 3600
5 Skilled technician Skilled technician 0.25 nos 1200 per day 1200 300
6 Carpenter Carpenter 0.5 nos 700 per day 700 350
7 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Carpenter helper 1.5 nos 550 per day 550 825
8 Scaffolding LS 300
9 Carrying to site in/c sundries LS 500
Sub-Total 8875
Contractor's Profit 10% 0.1 887.5
Contractor's Overhead Expenses 3.5% 0.035 310.63
Total 10073.13
Add VAT with adjustment factor. 1.08108 7.5% 0.075 816.74
Grand Total 10889.87
Rate per sft 108.9
Rate per sqm 1172.2