| SL# | Item Code | Item Description | Unit |
Rate for ZoneA Dhaka & Mymensingh Division |
Rate for ZoneB Chattogram & Sylhet Division |
Rate for ZoneC Rajshahi & Rangpur Division |
Rate for ZoneD Khulna & Barishal Division |
|---|---|---|---|---|---|---|---|
| DIVISION 09: PILE WORKS AND PILE TEST | |||||||
| 551. | 09.9.1 | For intermediate loading from 50 tonne to 100 tonne for each additional tonne | |||||
| 552. | 09.9.1.1 | For first test at one site for one testing set | tonne | 1200 | 1201 | 1191 | 1191 |
| 553. | 09.9.1.2 | For 2nd & additional tests at same site for same testing set | tonne | 1080 | 1081 | 1072 | 1072 |
| 554. | 09.9.2 | For intermediate loading from 100 tonne to 150 tonne for each additional tonne. | |||||
| 555. | 09.9.2.1 | For first test at one site for one testing set | tonne | 1173 | 1174 | 1166 | 1166 |
| 556. | 09.9.2.2 | For 2nd & additional tests at same site for same testing set | tonne | 1055 | 1056 | 1049 | 1049 |
| 557. | 09.9.3 | For intermediate loading from 150 tonne to 200 tonne for each additional tonne. | |||||
| 558. | 09.9.3.1 | For first test at one site for one testing set | tonne | 1214 | 1215 | 1204 | 1204 |
| 559. | 09.9.3.2 | For 2nd & additional tests at same site for same testing set | tonne | 1093 | 1093 | 1084 | 1084 |
| 560. | 09.9.4 | For intermediate loading from 200 tonne to 250 tonne for each additional tonne. | |||||