| Item Code and Name | Unit |
Rate for Zone-A Dhaka & Mymensingh Division |
Rate for Zone-B Chattogram & Sylhet Division |
Rate for Zone-C Rajshahi & Rangpur Division |
Rate for Zone-D Khulna & Barishal Division |
|
|---|---|---|---|---|---|---|
| 100.BATCHING AND READY MIX CONCRETE | ||||||
| 2159-Production cost of Ready Mix Concrete (excluding material cost) including carrying and pumping at site | per cum | 410 | 410 | 410 | 410 | Edit |
| 2160-Water reducing high range chemical (for batching/RMC) admixture Type G | per kg | 140 | 140 | 140 | 140 | Edit |
| 2161-Micro Silica (for high strength concrete) | per kg | 80 | 80 | 80 | 80 | Edit |
| 101.SECONDARY INPUT FOR RCC WORKS | ||||||
| 0-Materials (From Secondary Input : Item B-3) | 18275 | 0 | 0 | 0 | Edit | |
| 0-Laying/placing concrete (@ 1200 cft concreting using 1 mixer machine in one day) (From Secondary Input : Item A-1) | cft per day | 1657.916666 | 0 | 0 | 0 | Edit |
| 0-Laying/placing concrete (@ 800 cft concreting using 1 mixer machine in one day) (From Secondary Input : Item A-3) | cft per day | 2486.875 | 0 | 0 | 0 | Edit |
| 0-Laying/placing concrete (@ 1000 cft concreting using 1 mixer machine in one day)(From Secondary Input : Item A-2) | cft per day | 1989.5 | 0 | 0 | 0 | Edit |
| 0-Laying/placing concrete (@ 600 cft concreting using 1 mixer machine in one day)(From Secondary Input : Item A-4) | cft per day | 3315.833333 | 0 | 0 | 0 | Edit |
| 0-Materials (From Secondary Input : Item B-4) | 29466.5 | 0 | 0 | 0 | Edit | |
| 0-Materials (From Secondary Input : Item B-5) | 30248.5 | 0 | 0 | 0 | Edit | |