Item Rate Setting

Search

SL# EffectiveDate Item Code BasicItem RateA RateB RateC RateD
2211. Schedule of Rate-2023 2 Contractor's Overhead Expenses 0.035 0.035 0.035 0.035 Edit
2212. Schedule of Rate-2023 3 VAT 0.075 0.075 0.075 0.075 Edit
2213. Schedule of Rate-2023 4 Additional Incidental Expenses for Gas Line Installation Works 0.1 0.1 0.1 0.1 Edit
2214. Schedule of Rate-2023 1 Head mason / Mosaic head mistry 800 800 750 750 Edit
2215. Schedule of Rate-2023 2 Mason / Mosaic mistry 700 700 650 650 Edit
2216. Schedule of Rate-2023 3 Skilled labour 600 580 550 550 Edit
2217. Schedule of Rate-2023 4 Ordinary labour 550 540 500 500 Edit
2218. Schedule of Rate-2023 5 Field Engineer ( minimum BSc in Eng. with 3yrs exp OR Diploma in Eng. with 8yrs exp) 1900 1900 1900 1900 Edit
2219. Schedule of Rate-2023 6 Skilled technician 1200 1200 1200 1200 Edit
2220. Schedule of Rate-2023 7 Semi skilled technician 800 800 750 750 Edit
Help