| SL# | Item Code | Item Description | Unit |
Rate for ZoneA Dhaka & Mymensingh Division |
Rate for ZoneB Chattogram & Sylhet Division |
Rate for ZoneC Rajshahi & Rangpur Division |
Rate for ZoneD Khulna & Barishal Division |
|---|---|---|---|---|---|---|---|
| DIVISION 27 : DEEP TUBE-WELL | |||||||
| 1781. | Supplying the following tube well fixtures and pipes conforming to standard BS-1387 & BDS-1031, having chemical composition (in%) carbon 0.17-0.25, manganese 0.95-1.20, sulphur 0.060 max, phosphorous 0.060 max, tensile properties: miminum yield strength 188 MPa, minimum tensile strength 313 MPa and marking for a) manufacturer b) material c) wall thickness d) nominal outside dia e) intended use etc. on the body of the pipe at working site as per standard practice and accepted by the Engineer-in-charge. | ||||||
| 1782. | Pumping test of the well by designed turbine/submersible pump with supply of testing equipments for pressure/ velocity/ discharge etc. and all materials for 72 hours including yield drawn and recovery test etc. complete as per specification and accepted by the Engineer-in-charge. | hour | 1316 | 1313 | 1300 | 1300 | |
| 1783. | Disinfections of the well including supply of sufficient quantity of bleaching powder (33% strength) chlorinated water having 150 ppm available free chlorine etc. complete as per standard specification and accepted by the Engineer-in-charge. | each | 2877 | 2877 | 2877 | 2877 | |
| 1784. | Filling of the borehole around the tube well from top of the shrouding up to the bottom of sanitary seal by withdrawn selected soil or local clay free from any substances harmful to pipes and health as per standard specification and accepted by the Engineer-in-charge. | meter | 85 | 83 | 78 | 78 | |
| 1785. | INSTALLATION OF 200 mm x 400 mm DIA SHROUDED | ||||||
| 1786. | PRODUCTION WELL WITH G.I. PIPE | ||||||
| 1787. | Boring: Execution of 800 mm dia boring through all sorts of strata by reverse circulation or any other approved method (Method other than reverse circulation is to be applied only for wells deeper than 152 meter). For boring 800 mm dia vertical hole up to designed depth and collection of soil samples at every 3 meter interval and at every change of formation including sinking and withdrawing necessary casing pipe and all necessary arrangements complete as per specification and accepted by the Engineer-in-charge. (Measurement will be allowed form G.L. to bottom of the blind pipe and the rate is required for caving and siltation) | ||||||
| 1788. | Complete installation of 150 mm dia deep tube-well fixtures such as expanded top pipes, reducer, tube-well pipes, strainer, blind pipe, pipe cap etc. fitting and fixing socket, welding and additional welding with fibre and placing in position with proper size M.S. centralizer @ 3 meter c/c in strainer portion including. blind pipe etc. complete as per standard practice and accepted by the Engineer-in-charge. | meter | 805 | 790 | 732 | 732 | |
| 1789. | Complete development of the tube well by suitable air compressor and pump of suitable capacity by alternate surging and pumping until satisfactory yield, sand free water and the turbidity condition is reached using necessary quantity of calgon and conducting step draw down test before and after the development as per specification and accepted by the Engineer-in-charge. (Development should be started within 24 hours of completion of shrouding) | ||||||
| 1790. | Complete installation of 200 mm dia deep tube well fixtures such as expanded top pipes, reducer, and tube well pipes, strainer, blind pipe. pipe cap etc. Fitting and fixing socket, welding and additional welding with fibre and placing in position with proper size M.S. centralizer @ 3 meter c/c in strainer position including blind pipe etc. complete as per standard practice and accepted by the Engineer-in-charge. | meter | 879 | 863 | 799 | 799 | |