List of Long Schedules
SL# Item Code Item Description Unit Rate for ZoneA
Dhaka & Mymensingh Division
Rate for ZoneB
Chattogram & Sylhet Division
Rate for ZoneC
Rajshahi & Rangpur Division
Rate for ZoneD
Khulna & Barishal Division
DIVISION 06 : TILES, MARBLE AND GRANITE STONE WORKS
261. 06.2 Supplying, fitting and fixing country made mirror polished homogeneous floor tiles complying BDS ISO 13006: 2015, water absorption ≤ 0.5%, modulus of rupture (MOR) ≥ 27 N/mm2, irrespective of color &/or design, with 20 mm thick cement sand (F.M. 1.2) mortar (1:4) base and raking out the joints with white cement including cutting and laying the tiles in proper way and finishing with care etc. all complete and accepted by the Engineer-in-charge. (Cement: CEM-II/B-M) In ground floor
262. 06.2.1 GP (mirror polished) 400 mm x 400 mm floor tiles sqm 1719 1709 1677 1677
263. 06.2.2 GP (mirror polished) 500 mm x 500 mm floor tiles sqm 1858 1847 1815 1815
264. 06.2.3 GP (mirror polished) 600 mm x 600 mm floor tiles sqm 2038 2028 1996 1996
265. 06.2.4 GP (mirror polished) 800 mm x 800 mm floor tiles sqm 2177 2166 2134 2134
266. 06.2.5 GP (mirror polished) 600 mm x 900 mm floor tiles sqm 2440 2430 2398 2398
267. 06.2.6 GP (mirror polished) 600 mm x 1200 mm floor tiles sqm 2870 2860 2828 2828
268. 06.2.7 GP Mirror Polished (Double Charge) 600 mm x 600 mm floor tiles sqm 2260 2249 2218 2218
269. 06.2.8 GP Mirror Polished (Double Charge) 800 mm x 800 mm floor tiles sqm 2745 2735 2703 2703
270. 06.20 Marble stone flooring with Indian standard quality (Bansowara/ Indian grey/ Indian pink or equivalent) marble stone of approved quality complying accepted National/ International standards, texture and size with 25 mm thick cement sand (50% F.M. 1.2 and 50% F.M 2.2) mortar (1:2) including placing cement slurry below the stone, cutting the marble stone to desired size, grinding and finishing the edges, setting in position in proper level, filling the gaps with white cement and colouring pigments including supplying all necessary equipments/materials and finishing the top by pumice stone and necessary auxiliary materials and water, electricity and other charges complete in all respect and accepted by the Engineer in charge.(Cement: CEM-II/B-M).
Help