List of Long Schedules
SL# Item Code Item Description Unit Rate for ZoneA
Dhaka & Mymensingh Division
Rate for ZoneB
Chattogram & Sylhet Division
Rate for ZoneC
Rajshahi & Rangpur Division
Rate for ZoneD
Khulna & Barishal Division
DIVISION 26 : SANITARY & WATER SUPPLY WORKS
1701. 26.71 Construction and placement M.H. cover with locking/unlocking arrangement including necessary earth work, side filling, shuttering, curing, cement plaster (1:4) with neat finishing on edges and top etc. all complete approved and accepted by the Engineer- in- charge.
1702. 26.71.1 900 mm x 900 mm x 75 mm R.C.C. pit cover each 1144 1142 1126 1121
1703. 26.71.2 1025 mm x 1025 mm x 75 mm R.C.C. pit cover each 1320 1318 1300 1294
1704. 26.71.3 1100 mm x 1100 mm x 75 mm R.C.C. pit cover each 1512 1511 1491 1484
1705. 26.72 Construction and placing of R.C.C inspection pit cover (slab) with supplying and provisions for placing, fitting, fixing 450 mm dia C.I. man-hole cover with locking/un-locking arrangement including concrete (1:2:4) with approx. 1% re-enforcement, necessary earth cutting, or cleaning, side filling, curing etc. with minimum 12 mm cement plaster (1:4) and neat cement finishing on edges and top all complete and accepted by the Engineer- in- charge.
1706. 26.72.1 950 mm x 950 mm x 75 mm R.C.C. pit cover with 450 mm dia C.I. manhole cover. each 2073 2071 2057 2053
1707. 26.72.2 1025 mm x 1025 mm x 75 mm R.C.C. pit cover with 450 mm dia C.I. manhole cover. each 2248 2246 2230 2225
1708. 26.72.3 1100 mm x 1100 mm x 75 mm R.C.C. pit cover with 450 mm dia C.I. manhole cover. each 2441 2439 2421 2415
1709. 26.73 Construction of masonry inspection pits up to a depth of 700 mm with 250 mm thick brick work in cement mortar (1:4) including 100 mm thick R.C.C. top slab (1:2:4) with 1% reinforcement, man-hole cover with locking arrangement including necessary earth work, side filling and one brick flat soling. 75 mm thick (1:3:6) base concrete for making invert channel and 12 mm thick (1:2) cement plaster with neat finishing etc. all complete approved and accepted by the Engineer- in- charge.
1710. 26.73.1 Clear 450 mm x 450 mm and depth 450 mm to 600 mm, average 525 mm for single 150 mm dia R.C.C. pipes and 400 mm PVC pipe with pit cover and 450 mm dia C.I. man-hole cover. each 6122 6087 5938 5892
Help