List of Long Schedules
SL# Item Code Item Description Unit Rate for ZoneA
Dhaka & Mymensingh Division
Rate for ZoneB
Chattogram & Sylhet Division
Rate for ZoneC
Rajshahi & Rangpur Division
Rate for ZoneD
Khulna & Barishal Division
DIVISION 01 : GENERAL, SITE FACILITIES & SAFETY
31. 01.20 Construction of sanitary latrine of 1.5 sqm for labourers in the construction site including supply & installation of all equipments like 900mm dia RCC ring (300mm height), slab, pan with sanitary seal etc. as necessary with colored profile sheet roofing and walling arrangement with necessary water supply system. All complete as per direction of Engineer-in-charge. (Rate is inclusive cost of removing of the latrine & soak well after completion of contract and backfilling the pits with sand). each 27226.71 27153.09 26735.9 26735.9
32. 01.21 Supply and placing of waste bin (separate waste bins for organic, inorganic and hazardaous wastes) with necessary manpower support for proper disposal of wastes daily at the recommended place or city corporation/municipality damping ground area nearest to site. All complete as per direction of engineer in charge. each 5215 5215 5215 5215
33. 01.22 Supplying and providing of safety cover on the trench or drain during non-work hours with wood shutter including man-power support etc. all complete as per direction of the engineer in charge. sqm 123 120 122 122
34. 01.23 Erection & removal of labour shed of 40 sqm with CI sheet walling & roofing supported with local bamboo in a construction site for both male & female workers and also a breast-feeding area for female workers, floor soling, plaster with NCF (one room allocated for isolation purpose). All complete & accepted by the Engineer-in-charge. each 155832 155832 155832 155832
35. 01.24 Supplying, maintaining and ensuring safety measure for covid-19 or other infectious disease issue i.e. supplying of 3 nos. infra-red thermometers, soap/handsanitizer -4 nos/per site, sufficient manpower support for cleaning & washing the office/ work area and basin with soap with necessary water supply facility from the site. Also logistic support to frame an awareness meeting (i.e. health safety, gender violence, covid-19 or infectious disease issue etc.) between contractor and employer at the engineer's office at site. All complete & accepted by the Engineer-in-charge. per tender 70125 70125 70125 70125
36. 01.25 Providing of dust preventive measures by regular watering the site at materials required and also supplying and laying of hessian cloth/ polythene sheet or tripol to cover construction materials including manpower support (payments will be made only one time based on the available area for construction material stackyard). All complete & accepted by the Engineer-in-charge. per sqm 64 63 62 62
37. 01.3.1 Providing coloured progress picture & video of works, CCTV monitoring system operation and related data processing, regular data updating & all other relevent works regarding online monitoring system etc. per month 32498 32498 32498 32498
38. 01.3.2 Preparing & providing video documentary of completed project with video footage taken by expert professional videography team by drone/equivalent media including video editing, voice editing and relevant works. all complete and accepted by the Engineer-in-charge. (Payment will be made based on construction area) sqm 19 19 19 19
39. 01.4.1 Preparation & submission of work programme / schedule to the Engineer-in-charge for approval prior ground breaking showing the events (works) and successive sub-events of works including all the management & control parameters like Earliest Start Time (EST), Earliest Finish Time (EFT), float events on critical path, resource allocation etc. with description of general method of works, in orderly manner all in the form of network diagram prepared in computer software like MS project/ Primavera and presenting in displayable hard and soft copy minimum 3 (three) sets. (This is a time related item. Proportionate payment for this item shall be made distributing in each bill on the basis of percentage progress of the whole works under contract) per tender 32076 32076 32076 32076
40. 01.4.2 Updating the work programme and submission to the Engineer-in-charge at intervals no longer than 28 days showing actual physical and financial progress achieved on each activity and the effect of the progress on the timing of the remaining work, including any changes to the sequence of the activities.However, Engineer’s approval of the programme shall not alter the contractor’s obligations. The contractor may revise the programme and submit it to the Engineer-in-charge again at any time. A revised programme shall show the variations and events related to change of contract price. Month wise documentation shall be the basis of payments on this item. per month 6432 6432 6432 6432
Help