Long Schedule By Division

SL# Item Code Item Description Unit Rate for ZoneA Rate for ZoneB Rate for ZoneC Rate for ZoneD
DIVISION 01 : GENERAL, SITE FACILITIES & SAFETY
1. 01.1 Erection and maintenance of site office and removal of the same after completion of work in accordance with the conditions of contract. In addition to the office required for own use, the contractor shall provide and maintain furnished site office for the use of Engineer-in-charge and his staff. The site office must have tiles floor, adequate foundation, brick walls, false ceiling of gypsum board and all windows are to be glazed, shuttered and provided with steel grill. Outside and inside wall surface are to be painted on plaster acceptable to the Engineer-in-charge. The site office shall be maintained in a secure condition by the contractor until the completion of the contract and shall be provided with electricity, water supply, wash rooms and sewerage facilities. All doors shall be fitted with approved locks and windows shall be provided with screen/blinds. Before construction the contractor shall submit plans and drawings showing proposed details and location for the site office, including foundations, access roads, shades, layout of electrical and water supply and hard standings there for the approval of Engineer-in-charge. The Engineer-in-charge may require revision of the plans prior to giving approval for construction. The contractor shall also submit detailed proposed furniture, fittings and other items of equipment and plant to the Engineer-in-charge for approval. These items shall be of the standard quality suitable for site. The office, complete with furnishings, fittings, access roads and hard standings shall be ready for occupation by the Engineer-in-charge within 28 days of the date when the contractor first occupies the site. The contractor shall provide day and night guards and an attendant for the field office. At the end of the contract all materials, equipment and plant, furniture, fittings recovered from dismantling the office and removing access road will be the property of the contractor. No interim payment shall be certified unless engineer’s office with required facilities are constructed and accepted by the Engineer-in-charge. (This is a time related item; proportionate payment for this item shall be made distributing in each bill on the basis of percentage progress of the whole works under contract)
2. 01.1.1 Erection and removal of semi permanent Engineer's site office Show Breakup sqm 7524 7524 7524 7524
3. 01.1.2 Providing necessary facilities in site office including office furniture, 24000 BTU air cooler, umbrella, crookeries, water purifier, PC with monitor, uninterruptible power supply (UPS), laserjet printer (minimum 20 ppm), LED flood light fittings(Halogen) for sight security etc. Show Breakup job 204914 204914 204914 204914
4. 01.1.3.1 Providing necessary facilities in construction site for maintaining site safety of 30 nos construction worker including safety helmet, safety belt , apron, gumboot, goggles etc. Show Breakup set 38651 38651 38651 38651
5. 01.1.3.2 Providing necessary facilities in construction site for maintaining site safety of 10 nos construction inspection team member including safety helmet, safety goggles, safety shoe etc. Show Breakup set 10798 10798 10798 10798
6. 01.1.3.3 Supplying and providing of first aid box with necessary materials/medicine (hygienic gown , thermometer, adhesive dressings, antiseptic solutions, bandages, cotton balls or swaps,emergency blanket, gloves, hand sanitizer, ice pack, saline etc ). All complete as per direction of Engineer-in -charge. Show Breakup each 16215 16215 16215 16215
7. 01.1.4 Hiring, installation, testing & commissioning of CCTV/Surveillance facilities for monitoring construction site including supply, fixing of 5.0 megapixel IR fixed bullet network IP camera including lens, bracket, housing with outdoor night vision facilities, full HD 1080 pixel, real time video, network video recorder (NVR) , 2 TB HDD for NVR , 4/8/16/32 port PoE switch, 32"/42" Full HD CCTV monitor, cable & accessories, internet connection with operation & maintenance cost throughout contract completion period, re-fitting & re-fixing with progress of construction all complete as per direction of Engineer in charge Show Breakup job 49081 49081 49081 49081
8. 01.1.5 Providing and maintenance one project profile signboards to be placed at a suitable place of the site including submission of proposals for the materials of the signboards and text layout containing 3D picture, safety instructions, project information with security light etc to the Engineer-in-charge for approval which will be positioned as directed by the Engineer-in-charge and removing the same on completion of the works or as instructed by the Engineer-in-charge. Show Breakup sqm 3301 3276 3239 3239
9. 01.10 Providing transport facilities for quality control part of project which includes carrying test samples, work samples, report collection & emergency services of project including cost of fuel, driver, maintenance etc. (Total duration is 1/2 of the initial contract duration or contract completion time whichever is less ). per month 70000 70000 70000 70000
10. 01.11 Supplying, fitting, fixing, operating and maintenance of the construction supervision lift (1000Kg capacity) for supervision of building construction work during the entire construction period including all necessary components like, steel frame, car, guide rails. push button, driving motor, gear box, car door, travelling cable, RCC base for steel frame, necessary connections with the building, electric supply & electricity bill and dismantling the same after completion of the building construction etc. all complete complying all safety factors and accepted by the Engineer-in-charge. (The construction supervision lift shall be the contractor property after completion of work). Number of month shall be calculated as 1/2 (half) of the initial contract period or contract completion time whichever is less for new construction and full contract period for vertical extension work. The contractor must submit detail structural drawing of supporting frame with foundation and lift specification prior to supply on site.
11. 01.11.1 6th to 9th floor, hoisting speed 40 m/min Show Breakup per month 17730 19061 19061 19061
12. 01.11.2 10th to 14th floor, hoisting speed 40 m/min per month 21470 23609 23609 23609
13. 01.11.3 15th to 19th floor, hoisting speed 50 m/min per month 25153 28149 28149 28149
14. 01.11.4 20th to 24th floor, hoisting speed 60 m/min per month 29151 33034 33034 33034
15. 01.11.5 25th to 29th floor, hoisting speed 60 m/min per month 32419 37212 37212 37212
16. 01.12 Providing junior architect / project architect having minimum qualification Bachelor in Architecture with registration in respective professional body for detail documentation of architectural themes, drawings, workingout shop drawings, communication with theme architect & getting approval, specifying architectural needs according to approved master architectural themes & plan, certifying as built drawing for the approval etc. and any relevant jobs assigned by the HOPE or his official at site (payment for the item subject to submission of CV & approved by concerned circle Superintending Engineer & duration is initial contract period or contract completion time whichver is less). per month 50000 50000 50000 50000
17. 01.13 Providing junior engineer/project engineer having minimum qualification B.Sc. in Civil Engineering with registration in respective professional body for project documentation, progress study & adjustment, preparation of project material schedule and testing schedule for approval etc. & jobs assigned by the HOPE or his official, at site (payment for the item subject to submission of CV & approved by concerned circle Superintending Engineer & duration is initial contract period or contract completion time whichver is less). per month 50000 50000 50000 50000
18. 01.14 Supplying, fitting, fixing, operation & maintenance of minimum 5 ton tower crane including hook height maximum 45 m which can be extended upto 120 m by added no of mast. Minimum job radius is 50m. Maximum load capacity 5 ton near centre & 1 ton @ tip at 50 m. Crane structure & foundation should be safe enough to sustain against wind pressure & other loads. Crane Operation & maintenance include trained operator, helper, additional labour for materials placing & removing with necessary connections for electricity supply and dismantling the same after completion of building construction. (The contractor must submit detail structural drawing of supporting frame with foundation and tower crane specification prior to supply on site. All complete, approved & accepted by the Engineer-in-charge. Duration is initial contract period or contract completion time whichever is less .This item is mainly used for contruction material lifting in site. If this item is used in Engineer's Estimate, added charge for lifting construction material in different chapter of SoR must not be considered in Engineer's Estimate.)
19. 01.14.1 Height upto 45m Show Breakup per month 242881.8 242145.59 239200.72 239200.72
20. 01.14.2 Added rate for height increment every 3m after initial 45m per month 8333.33 8333.33 8333.33 8333.33
21. 01.15.1 Hire and Installation of Compression Testing Machine with necessary accessories, machine calibration for testing of concrete cylinders, with Compressive Strength Testing Machine of Rated Capacity: 2000kN, Four Column Frame, Frame Material: Mild Steel, High Frame Stiffness, Diameter of Each Column: Minimum 60 mm, Vertical Clearance: Minimum 320 mm, Piston Stroke: Minimum 100 mm, Piston Diameter: Minimum 250mm, Rated Pressure of the Hydraulic Pump: Minimum 40MPa, Size of the Bearing Plate: Minimum 320x260mm, Outside size: Minimum 950×400×1160mm, Max. piston lift speed: Minimum 50mm/min, Piston free back speed: Minimum 20mm/min, Weight of the Machine : Minimum 500KG, Noise: ≤80Db, Relative indication error: ±1%, Powersupply: 220VAC 750W, Sample Height would be adjusted by screw Column (Movable upper platen), Load Measurement: Load would be Measured Pressure Sensor, Digital Display would show the Current Load and Peak Load, The maximum force value can be maintained and the data measured can be saved when the power is off, The test data can be processed automatically and the test report can be printed, Machine Control: Machine Speed would be controlled by pressure Compensated flow Control Valve.; This item also includes steel unbonded caps for capping of specimen, Elastomeric neoprene pads for capping of specimen, Slide Calipers for measuring dia of specimen, Cylinder mold of 100mm x 200mm Side wall thickness: 5mm; 10mm tamping rod, 300mm long; Rubber mallet; Metal tray for concrete cylinder preparation etc. with required number test work. All complete & accepted by the Engineer-in-charge. (Rate is including the cost of Compression Testing Machine Initial Calibration. Calibration should be performed once in every 12 months) Show Breakup Per Month 7005 7367 7367 7367
22. 01.15.2 Additional charge for machine calibration after initial calibration Show Breakup Per Calibration 39878 39878 39878 39878
23. 01.16 Supply of Sieve Set with necessary accessories for Sieve analysis of Coarse Aggregate and Fineness Modulus determination of Fine Aggregate using various sieves as per specification of ASTM E11 (Sieve Sizes: 37.5mm, 25mm, 19mm, 14mm, 12.5mm, 9.5mm, 6.3mm, 4.75mm, 2.36mm, 1.18mm, 0.6mm, 0.3mm, 0.15mm, 0.075mm); Mixing tray; Weighing balance, 0.1g sensitivity, 16kg capacity; .All complete & accepted by the Engineer-in-charge. Show Breakup Per Set 50738 50738 50738 50738
24. 01.17 Supply of Slump test tools for Slump Test of Hydraulic-Cement Concrete as per ASTM C143/C143M Slump Mold set; 16mm tamping rod etc with required number test work. All complete & accepted by the Engineer-in-charge. Show Breakup Per Set 3804 3804 3804 3804
25. 01.18 Supply of construction measuring tool including 2 nos measuring tape of length 30m, 2 nos measuring tape of length 6m, 2 nos steel tape of length 6m, 2 nos slide callipers, 2 nos moisture meter, 2 nos distance meter etc. for site monitoring purpose. Show Breakup Per Set 15240 15240 15240 15240
26. 01.19.1 Performing concrete/brick/block compressive strength test including preparation of test sample and specimen, machine operation, relevant data collection and calculation, report preparation, carrying, handling and disposal of material and all other relevant works for on site assessment of building construction materials, test performance must be carried out by experienced lab engineer/technician following the direction of Engineer-in-charge. Show Breakup per set test 690 690 675 675
27. 01.19.2 Performing sieve analysis of fine and coarse aggregate including preparation of test sample and specimen, relevant data collection and calculation, report preparation,carrying, handling and disposal of material and all other relevant works for on site assessment of building construction materials, test performance must be carried out by experienced lab engineer/technician following the direction of Engineer-in-charge. Show Breakup per set test 911 911 891 891
28. 01.19.3 Performing concrete slump test, cone operation, carrying, handling and disposal of material and all other relevant works for on site assessment of building construction materials following the direction of Engineer-in-charge . Show Breakup per test 104 104 98 98
29. 01.2.1 Providing 3 sets as-built drawings subject to Engineer’s approval produced in AutoCAD software in 584.5 mm x 413.5 mm (A-2 size) standard drawing paper, and operating and maintenance manual of the equipment and plant incorporated in the works, if any, in original by the date stated in the particular conditions of contract (PCC). If the contractor does not supply the as-built drawings and operating & maintenance manuals by the date stated in the particular conditions of contract (PCC), or they do not receive the Engineer-in-charge’s approval, the Engineer-in-charge shall withhold the amount stated in the PCC from the payments due to the contractor. The as-built drawings must show the permanent works as actually constructed and reflect the revision of drawings supplied to the contractor during the Contract as well as revisions of drawings supplied to the contractor during the contract. (One set of as-built drawings shall be considered for measurement and payment) Show Breakup per tender 29095 29095 29095 29095
30. 01.2.2 Providing additional copy of as-built drawing produced in AutoCAD software in 584.5 mm x 413.5 mm (A-2) standard drawing paper accepted by the Engineer-in-charge. Show Breakup sqm of drawing sheet 331 331 331 331
31. 01.20 Construction of sanitary latrine of 1.5 sqm for labourers in the construction site including supply & installation of all equipments like 900mm dia RCC ring (300mm height), slab, pan with sanitary seal etc. as necessary with colored profile sheet roofing and walling arrangement with necessary water supply system. All complete as per direction of Engineer-in-charge. (Rate is inclusive cost of removing of the latrine & soak well after completion of contract and backfilling the pits with sand). Show Breakup each 27226.71 27153.09 26735.9 26735.9
32. 01.21 Supply and placing of waste bin (separate waste bins for organic, inorganic and hazardaous wastes) with necessary manpower support for proper disposal of wastes daily at the recommended place or city corporation/municipality damping ground area nearest to site. All complete as per direction of engineer in charge. Show Breakup each 5215 5215 5215 5215
33. 01.22 Supplying and providing of safety cover on the trench or drain during non-work hours with wood shutter including man-power support etc. all complete as per direction of the engineer in charge. Show Breakup sqm 123 120 122 122
34. 01.23 Erection & removal of labour shed of 40 sqm with CI sheet walling & roofing supported with local bamboo in a construction site for both male & female workers and also a breast-feeding area for female workers, floor soling, plaster with NCF (one room allocated for isolation purpose). All complete & accepted by the Engineer-in-charge. Show Breakup each 155832 155832 155832 155832
35. 01.24 Supplying, maintaining and ensuring safety measure for covid-19 or other infectious disease issue i.e. supplying of 3 nos. infra-red thermometers, soap/handsanitizer -4 nos/per site, sufficient manpower support for cleaning & washing the office/ work area and basin with soap with necessary water supply facility from the site. Also logistic support to frame an awareness meeting (i.e. health safety, gender violence, covid-19 or infectious disease issue etc.) between contractor and employer at the engineer's office at site. All complete & accepted by the Engineer-in-charge. Show Breakup per tender 70125 70125 70125 70125
36. 01.25 Providing of dust preventive measures by regular watering the site at materials required and also supplying and laying of hessian cloth/ polythene sheet or tripol to cover construction materials including manpower support (payments will be made only one time based on the available area for construction material stackyard). All complete & accepted by the Engineer-in-charge. Show Breakup per sqm 64 63 62 62
37. 01.3.1 Providing coloured progress picture & video of works, CCTV monitoring system operation and related data processing, regular data updating & all other relevent works regarding online monitoring system etc. Show Breakup per month 32498 32498 32498 32498
38. 01.3.2 Preparing & providing video documentary of completed project with video footage taken by expert professional videography team by drone/equivalent media including video editing, voice editing and relevant works. all complete and accepted by the Engineer-in-charge. (Payment will be made based on construction area) Show Breakup sqm 19 19 19 19
39. 01.4.1 Preparation & submission of work programme / schedule to the Engineer-in-charge for approval prior ground breaking showing the events (works) and successive sub-events of works including all the management & control parameters like Earliest Start Time (EST), Earliest Finish Time (EFT), float events on critical path, resource allocation etc. with description of general method of works, in orderly manner all in the form of network diagram prepared in computer software like MS project/ Primavera and presenting in displayable hard and soft copy minimum 3 (three) sets. (This is a time related item. Proportionate payment for this item shall be made distributing in each bill on the basis of percentage progress of the whole works under contract) Show Breakup per tender 32076 32076 32076 32076
40. 01.4.2 Updating the work programme and submission to the Engineer-in-charge at intervals no longer than 28 days showing actual physical and financial progress achieved on each activity and the effect of the progress on the timing of the remaining work, including any changes to the sequence of the activities.However, Engineer’s approval of the programme shall not alter the contractor’s obligations. The contractor may revise the programme and submit it to the Engineer-in-charge again at any time. A revised programme shall show the variations and events related to change of contract price. Month wise documentation shall be the basis of payments on this item. Show Breakup per month 6432 6432 6432 6432
41. 01.5 Providing all necessary logistic support to frame ‘monthly progress meeting’ between contractor/contractor’s representatives and employer / employer’s representatives at the Engineer-in-charge's office at site. Month wise documentation shall be the basis of payments on this item. Show Breakup per month 2425 2381 2205 2205
42. 01.6 Providing layout and carry over PWD bench-mark (BM) at site from nearby BM pillar, property lines, existing ground level (EGL), formation ground level (FGL), highest flood levels (HFL), plinth levels (PL), mean sea level (MSL), setting and marking all pillars, marker, pegs etc. showing and maintaining reduced levels (RL’s) including locating, establishing, protecting all public utilities within the premise of work and finally all to be presented in black and white. Show Breakup sqm 33 33 30 30
43. 01.7 Mobilization and cleaning site before commencing actual physical work and during contract period and demobilization after completion of the works under contract to be accepted by the Engineer-in-charge. This work shall also cover cleaning and clearing, cutting or filling, dressing the project area on and in the ground to an extent that all the events of works of the project can be executed smoothly in a working environment with a particular attention on safety and security in all respects, and to stockpile the end outcome to a place for disposal agreed by the Engineer-in-charge, where, payments are to be based on ground area determined by the Engineer-in-charge and be proportionate to the percentage progress of work under contract as a whole in all respects and approved by the Engineer-in-charge. Show Breakup sqm 218 214 198 198
44. 01.8 Providing expertised architect having minimum qualification Bachelor of Architecture and relevant experience(s) more than 5 years with registration in respective professional body for detail documentation of architectural themes, drawings, working out shop drawings, communication with theme architect & getting approval, specifying architectural needs according to approved master architectural themes & plan, certifying as built drawing for the approval etc. and any relevant jobs assigned by the HOPE or his official at site (max man month not greater than 1/2 of initial contract duration or contract completion time whichever is less & payment for the item subject to submission of CV & approved by HOPE or his authorized officer). per month 100000 100000 100000 100000
45. 01.9 Providing expertised engineer having minimum qualification B.Sc. in Civil Engineering and relevant experience(s) more than 10 years with registration in respective professional body for project documentation, progress study & adjustment, preparation of project material schedule and testing schdule for approval etc. & jobs assigned by the HOPE or his official, at site (max man month not greater than 1/2 of initial contract duration or contract completion time whichever is less & payment for the item subject to submission of CV & approved by HOPE or his authorized officer). per month 150000 150000 150000 150000
Help